Many embankment projects will be completed in 2025

Chủ nhật, 31/08/2025 | 19:49:02 [GMT +7] A  A

Currently, Long An Construction Investment Project Management Board is investing in many projects in the fields of agriculture and rural development.

The project to prevent landslides along the Vam Co Tay River in the Da Han Bay area (Long An ward) has now reached 93% of the volume

In 2025, the Project Management Board will continue to implement 11 projects carried over from previous years, without starting any new projects. The total investment capital for these 11 projects is more than 2,108 billion VND.

Including 1 dredging project of the Vam Co Tay River and 10 embankment projects: Anti-erosion and salinity embankment of the Vam Co Dong River in Ben Luc district; Embankment to protect the Vam Co Tay River from the new Tan An bridge to Da Han Bay (Long An ward); Embankment of the Nuoc Man canal (Long Huu commune); Embankment to prevent erosion of the Vam Co Tay riverbank(Khanh Hau ward); Embankment to prevent erosion of the Kien Tuong ward; handling of erosion of the Can Giuoc river bank (Can Giuoc commune); dredging the Vam Co Tay River from the Hong Ngu canal to Binh Chau hamlet, etc.

Up to now, 3 embankment projects have been 100% completed and are in the process of final settlement, including the embankment to protect the banks of the Vam Co Tay River (from the new Tan An bridge to the junction with the Da Han Bay embankment); the Nuoc Man canal embankment (East bank, Long Huu commune); and the project to handle landslides on the banks of the Can Giuoc River (Can Giuoc commune).

The embankment project is under construction

For the remaining 8 projects, it is expected to be completed by December 2025 at the latest.

According to the Long An Construction Investment Project Management Board, the total planned capital allocation in 2025 for 11 projects is more than 246 billion VND, of which provincial capital is more than 62 billion VND and central capital is more than 184.3 billion VND.

Since the beginning of the year, more than 79.3 billion VND has been disbursed, reaching 32.19% of the capital plan. It is expected to reach 50.5% the end of the third quarter and 100% by the end of the fourth quarter./.

By Le Duc - Translated by Lien Thanh